Valves can leak. When a line has to be positively isolated, for maintenance or between services, a solid plate goes between two flanges. ASME B16.48 covers these line blanks.

The three types

  • Spectacle blind (figure-8): a solid blank and an open spacer joined by a web, like a pair of glasses. Turn it to switch between open and closed. It stays in the line, so its position is visible at a glance.
  • Paddle blind: a solid plate with a handle, used to close the line.
  • Paddle spacer: a ring with a handle, the same thickness as the blind, put in its place when the line is open so the piping does not have to close the gap.

Spectacle or paddles?

Small and medium sizes usually use spectacle blinds, because they are one piece and cannot get lost. On large sizes a spectacle becomes too heavy to handle, so a paddle blind and paddle spacer are used instead. The size where the change happens is set in the project specification.

Positive isolation

A closed valve is not proof against leaks. For work inside equipment or on a line, safety procedures often require a blind, a removed spool, or a double block and bleed. The blind must be rated for the line's pressure and temperature.

Layout points

  • The flanges must be able to spread apart: use jack screws or design enough flexibility into the piping.
  • Leave room for the spectacle to swing, and reach it from a platform or grade.
  • Put the blind on the equipment side of the isolation valve, and drain and vent the space between them.

Common questions

Why is it called a figure-8?

The blank and the open ring joined by a web look like the number 8, or a pair of spectacles.

Do I need longer bolts with a spectacle blind?

Yes. The blind adds its thickness plus an extra gasket to the joint, so the studs must be longer.

When is a paddle blind used instead of a spectacle?

On large sizes, where a one-piece spectacle would be too heavy to handle safely. The project specification sets the size.