Cable trays on a pipe rack: tier, clearances and hot lines

Most cables in a process unit ride on the pipe rack. Piping lays out the rack, so piping has to leave the right space for the trays and keep the cables away from heat and leaks.

Which tier

Cable trays usually go on the top tier of the rack, or a dedicated tier of their own. Up there they are away from leaks dripping from flanges above, less exposed to a fire at grade, and easy to drop down to the equipment they serve.

Separating trays

  • Power and instrument cables run in separate trays, spaced apart or with a barrier, so power cables do not disturb instrument signals.
  • The electrical and instrument engineers give the tray count and widths. Common widths are 150, 300, 450 and 600 mm.
  • Leave spare width for future cables; many projects reserve 20 to 30%.

Clearances

  • Leave space above each tray to lay and pull cables, often around 300 mm.
  • Keep trays clear of uninsulated hot lines and the flare header. Heat reduces how much current a cable can carry, and the electrical engineer has to derate it.
  • Do not run trays directly under flanges, valves or drains of flammable or corrosive lines.

Watch out for

  • Expansion loops are often turned up over the top tier. If trays are there too, plan where the loops cross them.
  • Drops: trays leave the rack at equipment and buildings. Keep those drop zones clear of pipes.
  • Supports: trays have their own supports. Do not use them to support pipes, or pipes to support trays.

Common questions

Why are cable trays on the top tier?

They stay out of the drips from flanges above, are less exposed to fires at grade, and drop easily to the equipment.

Can power and instrument cables share a tray?

Normally not. They are kept in separate trays or behind a barrier to avoid interference.

How much spare space should a tray have?

Many projects keep 20 to 30% spare for future cables. The electrical specification sets it.

More guides

Still have a doubt?Ask Pipe Ref. Clear questions get a reply, and the best ones become new guides, without your name.
Ask a question

General engineering guidance for learning and early design. Your project specifications and the governing code edition always take precedence.